The dispute over enhancement charges in Mohali’s IT City continues, as the Greater Mohali Area Development Authority (GMADA) has once again postponed a crucial meeting with plot allottees.
The meeting, scheduled for November 20 at PUDA Bhawan, was intended to explain the calculation and recovery process of enhancement charges. However, allottees received a cancellation message just one day before the scheduled meeting.
According to reports, GMADA also published a public notice announcing the cancellation. The authority cited administrative and departmental engagements as the reason for postponing the meeting.
The repeated postponements have left thousands of plot owners frustrated. Around 7,000 allottees and transferees are reportedly affected by the enhancement decision, including nearly 200 industrial plot holders.
The major point of concern is the proposed enhancement charge of Rs 7,845 per square yard. Plot owners have been demanding a detailed explanation of the formula used to calculate this amount.
They have also raised questions regarding land acquisition compensation, additional payments following court orders, development charges and the interest being demanded for previous years.
Earlier, a meeting was held on September 15, but the allottees claimed that their questions were not answered satisfactorily. A subsequent meeting scheduled for September 29 was also cancelled. The November 20 meeting has now been postponed as well.
The matter is already linked to proceedings before the Punjab and Haryana High Court. On August 27, 2026, the court quashed GMADA’s earlier enhancement demand notices, observing that the allottees had not been given a proper opportunity to present their side.
However, the court allowed GMADA to initiate a fresh demand process after following the due legal procedure.
Meanwhile, area councillor Nasib Singh Sandhu has said that plot owners are preparing to approach the Punjab and Haryana High Court again over the repeated delays and lack of clarity.
The big question now is when GMADA will hold the next meeting and provide a transparent explanation of the enhancement charges.
For thousands of affected plot owners, the wait for clear answers continues.